Kayak Fishing Adventures on Big Water’s Edge  

Go Back   Kayak Fishing Adventures on Big Water’s Edge > Kayak Fishing Forum - Message Board > General Kayak Fishing Discussion

Reply
 
Thread Tools Display Modes
Old 05-22-2014, 12:13 AM   #1
Sdspeed
Senior Member
 
Join Date: Sep 2012
Location: San Diego
Posts: 732
LJ Construction Update: 5/21/2014

I got this from the city late last night.

The concrete pour of the street, curb and gutter on Avenida De La Playa has been taking place for the past couple of days. The concrete needs to cure and pass pressure testing before the street will be reopened to traffic. There is a very good possibility that the curing is going to continue through the Memorial Holiday weekend and will remain off limits to vehicles until Tuesday. For the time being, keep an eye on street closure and detour signs and also watch for an email late Friday afternoon for an update on the results of the latest pressure test.
The La Jolla Beach and Tennis Club has been very understanding of the concrete curing situation and will extend parking privileges to the residents of 2110 and 2120 Avenida De La Playa through Memorial Day.
The water main that runs to the intersection of Avenida De La Playa and Camino Del Sol has been reconnected. When it passes bacteria testing it will be put into service and highlines will be removed.
The Sea Shell finish for the outfall structure will continue through May 22 and work crews will demobilize from the outfall/boardwalk area on Friday, May 23.
Concern has been raised by beachgoers and the kayak vendors about debris in the sand at the outfall structure. The contractor will knock down the berm in that area by the end of this week and will sift through the sand to remove the debris.

For Group Job 809, sewer main and lateral installation on Paseo Del Ocaso from Avenida De La Playa to Vallecitos will continue through Friday, May 23. The contractor has assigned extra crews to finish the work and clean up the street before the start of the Holiday weekend.
On Tuesday, May 27, construction activity for Group Job 809 will shift to the east of La Jolla Shores Drive on Vallecitos, Avenida De La Playa and Paseo Dorado. On Tuesday, May 20, Notices of Construction were distributed to houses on those streets that are within 300 feet of the upcoming work.

Last edited by Sdspeed; 05-22-2014 at 12:34 AM.
Sdspeed is offline   Reply With Quote
Old 05-22-2014, 07:29 AM   #2
TJones
Senior Member
 
TJones's Avatar
 
Join Date: Jan 2012
Posts: 2,526
ahead of schedule ?

thanks for you time and effort . how did you manage getting direct information from them so rapidly ?
TJones is offline   Reply With Quote
Old 05-22-2014, 10:58 AM   #3
Joctane
H2Okie Fanatic
 
Joctane's Avatar
 
Join Date: Apr 2011
Location: Tierrasanta
Posts: 52
Nice. Can't wait to finally start taking the PA out. Didn't feel like navigating through people and lugging that load off the beach. I can finally be lazy and drop that sucker right on the sand. This will also allow us to start watching people getting stuck in the sand again, myself included (I knew I should have paid extra for 4wd on my truck)
__________________
Give a man a fish and he will eat for a day. Teach him how to fish and he will sit in a boat and drink beer all day!
Joctane is offline   Reply With Quote
Old 05-22-2014, 02:07 PM   #4
FISH11
Member
 
FISH11's Avatar
 
Join Date: Aug 2013
Location: Pine Valley when not fishing La Jolla
Posts: 2,643
Thanks for the update. Sounds like next week after Teusday things will be closer to normal. It sure is nice to be able to unload and re-load right on the sand, can't wait.
__________________
MARK ......... 2016 MALIBU X FACTOR, 2020 SOLO SKIFF (Fishing Kayak on Steroids )
FISH11 is offline   Reply With Quote
Old 05-22-2014, 02:28 PM   #5
CKallday71
Senior Member
 
CKallday71's Avatar
 
Join Date: Feb 2013
Location: The 951
Posts: 430
Phenominal! That means that the first week of June it sould be cleaned up for me!
__________________
I fish therefore I am.
Selling cars since 2006. If you love what you do you never WORK a day in your life.
CKallday71 is offline   Reply With Quote
Old 05-23-2014, 12:16 PM   #6
driftwood
Senior Member
 
driftwood's Avatar
 
Join Date: Feb 2009
Location: SAN DIEGO
Posts: 1,086
feel free to use the launch its open now.
driftwood is offline   Reply With Quote
Old 05-23-2014, 12:39 PM   #7
bolocop
Senior Member
 
Join Date: Aug 2012
Posts: 332
Awesome! It looks great on the webcam, couldn't tell if the launch was open though. Thanks for the info!
bolocop is offline   Reply With Quote
Reply

Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is On

Forum Jump


All times are GMT -8. The time now is 08:26 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
© 2002 Big Water's Edge. All rights reserved.